Dholera solar park in 2026: 300 MW live, 1,000 MW sanctioned, 5,000 MW targeted
Dholera's confirmed operational solar capacity is Tata Power's 300 MW plant, live since April 2022. A 1,000 MW first phase is sanctioned (CEA, September 2025), and the ultimate target for the Dholera Ultra-Mega Solar Power Park is 5,000 MW by around 2030, not installed. Broader commissioned totals are reported but do not reconcile.
As of mid-2026, Dholera's solar story has one confirmed anchor and a much larger plan behind it. Tata Power Renewable Energy's 300 MW plant has been running since April 2022, a 1,000 MW first phase is sanctioned, and the ultimate target for the Dholera Ultra-Mega Solar Power Park is 5,000 MW.
What is actually generating
The confirmed operational capacity is the Tata Power Renewables 300 MW plant, commissioned in April 2022 with 873,012 monocrystalline modules across about 1,320 acres, described at commissioning as India's largest single-axis tracker installation. That is the piece you can point to as live today.
What is sanctioned and what is targeted
- The park was approved around April 2018.
- A Phase-1 of 1,000 MW is sanctioned, confirmed in the CEA's September 2025 solar parks record, with Gujarat Power Corporation Ltd as the agency.
- The ultimate target is 5,000 MW, or 5 GW, aimed at around 2030 and not installed.
Beyond the confirmed 300 MW, broader commissioned figures of roughly 1,000 to 1,200 MW have been reported, with around 700 MW said to be stalled on land or power-purchase issues in mid-2025. Those totals do not reconcile cleanly across sources, so we hold to the confirmed 300 MW as the operational number and flag the rest as reported.
Why the distinction matters
The solar park is one of Dholera's genuine on-ground anchors, alongside the Tata semiconductor fab under construction, the expressway reported open and the Activation Area's trunk infrastructure. But a 5,000 MW target is exactly that, a plan aimed at around 2030, and it is often quoted as if it were installed capacity. Clean power at scale is part of the pitch to energy-hungry industries such as semiconductors and electronics, so the park's build-out and the fab's ramp are linked stories. When we can confirm a new tranche against the CEA record or a developer commissioning notice, we will move that megawatt figure from target or reported to confirmed, and not before.
For the full history and technology of the park, see our Dholera solar park deep dive. For how power and services reach the city, read Dholera utilities and facilities, and for the wider industrial mix, read what industries are coming to Dholera.
Sources
- tatapower.com (300 MW plant, commissioned April 2022, module and area detail).
- CEA, September 2025 Solar Parks quarterly (Phase-1 1,000 MW sanctioned, GPCL agency).
- Press reports, mid-2025 (broader commissioned totals and stalled capacity, not reconciled).