Ten Dholera indicators worth tracking every month, with the place to read each one
Updated 11 November 2026. Compiled by the SIR Dholera desk from the sources listed at the end of this page.
Ten public indicators show whether Dholera is moving: the airport licence and schedule, Tata fab milestones, solar commissioning, the government monitoring report, GujRERA registrations, DSIRDA tenders, jantri notices, rail tenders and awards, expressway tolls and land allotments. Each has a free source. On 11 November 2026 the airport, rail, toll and jantri readings are all still waiting for an official notice.
The ten indicators
| Order | Indicator | What it measures | Where to read it | Reading on 11 November 2026 |
|---|---|---|---|---|
| 1 | Airport licence and airline schedule | Whether the airport can legally run flights | Airports Authority of India newsroom and the aviation regulator | Not open. Target of end of 2026 reported on 16 October 2026; no licence reported |
| 2 | Solar commissioning | Megawatts in operation out of 1,000 MW sanctioned in Phase I | NICDC monitoring report and the Central Electricity Authority | About 300 MW at 30 June 2026 |
| 3 | Government monitoring report | Land allotted, packages funded, land transferred | NICDC Delivery Monitoring Unit report (a monthly form; not every month is public) | 14 plots and 545 acres allotted at 30 June 2026 |
| 4 | GujRERA registrations | Registered plotted and building projects in Dholera | GujRERA project search at gujrera.gujarat.gov.in | 33 registered projects in the August 2026 extraction |
| 5 | DSIRDA and DICDL tenders | Public works being bid, awarded or built | dholera.gujarat.gov.in tender pages | A Rs 438.74 crore raw water reservoir announced 3 November 2026, no contractor named |
| 6 | Tata fab milestones | Progress at the largest single project | Tata Electronics newsroom and PIB | Commercial production reported for mid-2028; piping work began, reported 6 November 2026 |
| 7 | Rail tender and contract award | Whether the approved 134 km line has moved to construction | PIB, railway tender portals | Approved 13 May 2026; an EPC tender was reported on 3 August 2026 (India Shipping News); no construction start reported |
| 8 | Expressway toll notification | Cost of the road for cars | NHAI notifications | No rate for cars found in the record |
| 9 | Jantri notice | Government minimum land values | Gujarat revenue department notices | No new notification found; reports say the 15 April 2023 rates apply |
| 10 | New land allotments | Which companies have been given land | DICDL announcements and the monitoring report | No new allotment to a named company found from August to November 2026 |
1. Airport licence and airline schedule
- Latest readingNot open as of 11 November 2026
- Reported targetEnd of 2026
Dates for the airport have moved before, so the reading that matters is a licence and a published schedule. Neither has been reported. In reports of about 4 November 2026 an operation and management agreement between the Airports Authority of India and the airport company was reported, with no terms stated.
2. Government monitoring report
- PublisherNICDC, under the Delivery Monitoring Unit
- Latest in our record30 June 2026
This is the most useful single page for a buyer. It states the planned area, the activation area, the funding released and the land allotted. Reading two consecutive months shows what actually changed.
3. GujRERA registrations
- Registered projects33
- Extracted4 August 2026
A project must be registered before it is marketed. The portal shows the registration number, the promoter, the declared completion date and quarterly filings. A project you are offered should appear here.
4. Jantri notice
- Latest rates in forceThe 15 April 2023 doubled rates, per available reports
- RevisionNo new notification found
Jantri is the government's minimum value for registration. A revision would change the stamp duty base for every plot. Watch for a notification and read the rate for your survey number, not a summary.
How to use these in a monthly check
Set aside twenty minutes once a month. Open the monitoring report, the DSIRDA tender page and the GujRERA search, then scan the newsroom pages for the airport and the fab. Write down the date of each change. After three months you will see which indicators move and which only produce targets.
What a reading can and cannot tell you
An indicator shows that a public project moved. It does not show what any plot is worth, and it does not promise a return. A project can also move without helping a given village. Always tie a reading back to the scheme and village of the plot in question.
Before you pay for a plot
Verify the GujRERA registration, the title and the price for the exact plot.
What this list cannot tell you
These indicators track public projects and notices. They cannot tell you the title of a plot, its price or what it will be worth in future.
Questions people ask
How can I track Dholera's progress myself?
Use public sources once a month: the NICDC monitoring report for land and funding, the DSIRDA tender page for works, GujRERA for registered projects, and the newsroom pages of the Airports Authority of India and Tata Electronics. Note each date so changes are visible.
Where can I check whether a Dholera project is RERA registered?
Search the GujRERA portal at gujrera.gujarat.gov.in by project or promoter name. In the August 2026 extraction the Ahmedabad district list showed 33 registered projects for the Dholera SIR area. A project that is marketed but absent from the portal needs an explanation.
What is the best sign that Dholera airport will open?
A licence from the aviation regulator and a published airline schedule. As of 11 November 2026 neither has been reported, though a target of end of 2026 was reported on 16 October 2026.
Are Dholera jantri rates changing?
No new notification was found as of 11 November 2026. Available reports say the rates doubled on 15 April 2023 continue to apply and that a revision is pending. Check the Gujarat revenue department for the rate of a specific survey number.
Read next
Sources
- NICDC Delivery Monitoring Unit report (30 June 2026)
- GujRERA project register (extracted 4 August 2026)
- DSIRDA and DICDL portal (checked November 2026)
- CAPA: AAI and DIACL sign O&M agreement (4 November 2026)