Can you live in Dholera now? What is open, what is under construction and what has no date

Updated 11 November 2026. Compiled by the SIR Dholera desk from the sources listed at the end of this page.

People live in the 22 villages of Dholera SIR, but the planned city is still being built. At the Chief Minister's review on 16 October 2026 a 200-bed hospital, an integrated school, a hotel, a 42-room guest house, a 600-person food court, a tent city and a fire station were described as being developed in the activation area. None was reported complete. The airport is not open. Status as of 13 November 2026.

Living in Dholera: facility by facility

FacilityWhat was reportedStatus in the recordSource and date
Existing villages22 villages notified as the SIR area in 2009; residents live in them todayOccupied; village level services varySIR notification schedule, 2009
Hospital200-bed multi-speciality hospital in the activation areaBeing developed; completion not reportedIANS via NewKerala, 16 October 2026
SchoolIntegrated school in the activation areaBeing developed; opening not reportedIANS via NewKerala, 16 October 2026
Hotel and guest houseOne hotel and a 42-room guest houseBeing developed; room count of the hotel not reportedIANS via NewKerala, 16 October 2026
Food court and tent city600-person food court and a 50-tent tent cityBeing developedIANS via NewKerala, 16 October 2026
Fire stationListed among the social infrastructureBeing developed; no detail givenIANS via NewKerala, 16 October 2026
AirportDholera International AirportNot open; expected to be operational by the end of 2026IANS via NewKerala, 16 October 2026
Raw water reservoir2,200 million litre reservoir with pumping station, estimate Rs 438.74 crore, 18 month buildAnnounced only; no contractor namedDeshGujarat, 3 November 2026

Download this table (CSV). Last checked 11 November 2026. Free to quote with a link to this page.

Who lives in Dholera today?

The SIR covers 22 villages named in the 2009 notification, and families live and farm there. Facilities in those villages are those of ordinary Gujarat villages. Our Dholera taluka page explains how the village administration and the SIR authority fit together.

What is being built for residents?

The Chief Minister inspected social infrastructure in the activation area on 16 October 2026. The report lists a 200-bed hospital, an integrated school, a hotel, a 42-room guest house, a 600-person food court, a 50-tent tent city and a fire station. The report says these are being developed and does not confirm that any is complete. Local portals mention target dates, for example December 2026 for the hospital, but we treat those as unconfirmed.

What about water and power?

A 2,200 million litre raw water reservoir was announced on 3 November 2026 at an estimate of Rs 438.74 crore. The report does not say the work has been awarded. The seawater desalination plans are at the planning stage. We found no published household connection figures for the activation area.

Can you reach Dholera easily?

The Ahmedabad to Dholera expressway was inaugurated on 31 March 2026. The airport is not open, and the semi-high-speed rail line has been approved but no construction start has been reported. Details are on our page on how to reach Dholera.

Should you plan to move now?

On the record above, a family that needs a hospital, school and shops within a short distance will find the services still arriving. Decisions about moving, buying or renting should rest on what is open on the day you visit. Verify any plot through the verification guide. Nothing on this page predicts when the city will be lived in, and no return is promised.

What this page cannot tell you

This page relies on one wire report of the 16 October 2026 review and on one regional news report. It cannot say which facilities have opened since, or what rent, housing or utility connections are available.

Questions people ask

Is anyone living in Dholera smart city?

Yes, in the 22 villages of the SIR, which are occupied villages. The new city's housing and services are still under development, and the record we found does not report completed residential neighbourhoods.

Is there a hospital in Dholera?

A 200-bed multi-speciality hospital was reported under development in the activation area on 16 October 2026. Completion was not reported. See our hospitals page for health centres near the SIR.

Is there a school in Dholera?

An integrated school in the activation area was reported under development on 16 October 2026. Village schools exist in the villages. Opening of the new school was not reported.

Are there hotels in Dholera?

One hotel and a 42-room guest house were reported under development on 16 October 2026, with a 50-tent tent city. None was reported open.

Is Dholera airport open?

No. Officials said on 16 October 2026 that it is expected to be operational by the end of 2026. No airline schedule had been reported as of 13 November 2026.

Read next

Sources

  1. IANS via NewKerala, Gujarat CM takes stock of projects in Dholera region (16 October 2026)
  2. DeshGujarat, Dholera to get 220 crore litre raw water reservoir (3 November 2026)
  3. Dholera SIR official portal, frequently asked questions (read 13 November 2026)